The footers are now in, rebar put in place and the site is ready for the basement walls.
Once the rebar was in place, they began to install the forms and the shape of a basement began to emerge! The walls will be concrete poured into specially constructed aluminum forms. The forms were put up today and are locked into place. The plans are to pour the concrete which should be delivered on Friday November 15.
Materials have now been delivered to complete the final stages of Phase 1. This final stage will include the steel beam, posts, floor joists and decking to completely enclose the basement from the top. Provision will be made for plumbing and other services, and then the basement floor will be poured.
We are happy to report that the building inspector has been by and is pleased with the progress and quality of work to date. We have been cleared to continue! Phase 2 of the project will include framing and sheathing the walls, adding roof trusses, sheathing and shingling the roof and enclosing the building against the winter weather. More updates will follow soon! Thanks for your continued prayers for wisdom and safety.
Yay! Excited for you! Are you hoping to get in this winter or not until Spring?
ReplyDeleteyipee!!!!
ReplyDeleteWell at this point, I can say with some certainty we will not be finished this winter! Lord willing, we hope to have the house roofed and enclosed before the end of this year and will then be able to work through the early part of next year to complete the interior. We are happy to see the progress so far!